Design Review, ESIA and Construction Supervision for the Upgrading of Mchinji – Kawere Road to Bitumen Standard Financed by the EU - EDF

Prepared and submitted:

  • Draft Design Review Report including, Materials report, ESIA and Draft Bidding Documents
  • Final Design Review Report including Materials report and Draft Bidding Documents
  • Bidders’ prequalification Report
  • Bid evaluation report
  • Works contracts documentation for signature
  • Works quality control and progress monitoring
  • Measurements and certification of payment
  • Minutes of monthly progress site meetings
  • Monthly progress reports
  • Issued payment certificates
  • Claims assessment

Design Review, ESIA and Construction Supervision for the Upgrading of Mchinji – Kawere Road to Bitumen Standard Financed by the EU - EDF

Client The Chief Executive Officer, Roads Authority
Date May 2010 – Dec. 2012
Category Design Review
Country of Assignment Malawi
Value USD 0.510 million
Role Sub Consultant